Thursday, March 14, 2013
Henley Construction Company has reported that they have:
- Pepco set transformer and continues permanent power installation
- Poured Stair #1
- Continued spray fireproofing
- Continued with air barrier, all areas
- Continued fiber cement cladding
- Started exterior standing seam wall panels
- Continued with standing seam metal roof
- Continued with curtain wall/storefront frame/glass installation
- Completed stone veneer at retaining wall
- Continued with interior/exterior stone veneer and split face cmu
- Continued pluming rough in, all areas
- Continued electric rough in, all areas
- Continued duct work installation, all areas
- Measured interior storefront frames/began fabrication
- Continued sprinkler mains and branches, all areas
- Started hanging drywall first and second floors, north end
- Started building elevator shaft on stair one walls
- Continued roofing deficiency repairs, per Gale reports
Posted by Kay Bowman
POSTED: 9:51:00 AM
|
Tuesday, February 26, 2013
Henley Construction Company has reported that they have:
- Started upper level spray fire proofing
- Continued with air barrier, all areas
- Installation of fiber cement panel
- Continued metal roof installation
- Continued window installation
- Continued interior stone veneer on exterior cmu
- Continued pluming rough ins, all areas
- Continued with electric rough ins, all areas
- Continued with duct installation, south end
- Started sprinkler mains and branches, 1st/2nd floors
- Installed coiling door supports and doors, 1st/2nd floors
- Installed switchgear
- Connected storm lines from bldg to flow splitter 1
- Began fixing roof deficiencies per Gail Reports
Posted by Kay Bowman
POSTED: 1:27:00 PM
|
Tuesday, February 19, 2013
Henley Construction Company has reported that they have:
- Finished interior spray fire proofing 1st floor SW/SE
- Continued with air barrier
- Continued with fiber cement system mock-up
- Started exterior windows and curtain wall first floor
- Finished low roof installation at green roof/canopies with exception of deficiency items
- Continued electric rough-ins all areas
- Started ductwork mains south west side
- Continued with plumbing rough-in all areas
- Started sprinkler rough-in at basement
- Continued interior wall framing
- Continued with stone veneer
- Continued electric rough-ins 2nd and 3rd floors
Posted by Kay Bowman
POSTED: 2:24:00 PM
|
Wednesday, January 30, 2013
Henley Construction Company has reported that they have:
- Finished low roof fireproofing 1st floor SW/SE;
- Finished fiber cement panel mock up;
- Started exterior window installation;
- Finished low roof installation except some flashings around other trades;
- Continued elect rough-in all areas;
- Started duct work, 1st floor SW;
- started sprinkler rough-in at basement Interior wall framing;
- Continued interior stone veneer; and
- Continued electric rough-ins, 2nd and 3rd floors
Posted by Kay Bowman
POSTED: 3:33:00 PM
|
Wednesday, January 16, 2013
Henley Construction Company reports that they have
- Installed steel framing enclosure, chiller area
- Completed interior spray fireproofing 1st Floor SW
- Started 1st floor SE spray fireproofing
- Continued installing air barrier;
- Continued interior wall framing;
- Started mock up for fiber cement panels
- Started window flashings
- Continued with low roof installation
- Continued with electric panel equipment main electric room
- Continued testing and installing ducts
- Continued mechanical and plumbing rough-in all areas
- Started stone veneer, and
- Started electric rough-ins on second floor.
Posted by K. Bowman
POSTED: 11:35:00 AM
|
|