During this period, Milestone Construction Company:

  • Installed MH2A and continued backfill;
  • Installed telecommunications ductbank;
  • Installed Area 1 and Area 2 slab; and
  • Continued installation of high roof sheathing.

Posted by J. Eagan

POSTED: 1:12:00 PM |

Wednesday, February 27, 2013

January 10, 2013 to January 23, 2013

During this period, Milestone Construction Company:

  • Continued under-slab electrical work and slab prep at Area 2 slab-on-grade;
  • Continued installation of wood roof blocking;
  • Continued installation of masonry at mezzanine level;
  • Started new masonry openings at wall along 1-gridline; and
  • Continued installation of roof curbs for mechanical equipment.

Posted by J. Eagan

POSTED: 1:04:00 PM |

Friday, January 11, 2013

December 13, 2012 to January 9, 2013

During this period, Milestone Construction Company:

  • Continued duct bank work;
  • Worked on under slab electrical installation in Area 1;
  • Continued masonry wall work;
  • Poured the mezzanine slab; and
  • Did miscellaneous steel and mechanical piping work for the radiant heaters.

Posted by R. Gale

POSTED: 4:14:00 PM |

Tuesday, January 08, 2013

November 29-December 12, 2012

During this period, Milestone Construction Company:

  • Continued wood decking installation;
  • Started masonry wall repair near meeting room;
  • Started preparing the slab on grade in the Children's area;
  • Completed electrical conduit work;
  • Dug the trench for the ductbank;
  • Completed removal of existing roofing from gridlines 1 to 2;
  • Started rebar installation and prep work for the mezzanine slab; and
  • Completed excavation for metal vault installation. 

Posted by R. Gale

POSTED: 9:10:00 AM |

Tuesday, January 08, 2013

November 15-November 28, 2012

During this period, Milestone Construction Company:

  • Continued installation of glu-lam beams and wood decking;
  • Installed water line up to vault location;
  • Installed roof eave curved edge angle; and
  • Began waterproofing at foundation and underground plumbing inside the building. 

Posted by R. Gale

POSTED: 9:07:00 AM |
Entrance of the renovated Olney Library
Olney Library Renovation View of Entrance
Categories
 

Library Policies | Friends of the Library | Library Board | Library Jobs | Contact Us

Last edited: 11/6/2007