Gaithersburg Library Renovation


Construction updates

Thursday, March 14, 2013

February 27-March 13, 2013

Henley Construction Company has reported that they have:

  • Pepco set transformer and continues permanent power installation
  • Poured Stair #1
  • Continued spray fireproofing
  • Continued with air barrier, all areas
  • Continued fiber cement cladding
  • Started exterior standing seam wall panels
  • Continued with standing seam metal roof
  • Continued with curtain wall/storefront frame/glass installation
  • Completed stone veneer at retaining wall
  • Continued with interior/exterior stone veneer and split face cmu
  • Continued pluming rough in, all areas
  • Continued electric rough in, all areas
  • Continued duct work installation, all areas
  • Measured interior storefront frames/began fabrication
  • Continued sprinkler mains and branches, all areas
  • Started  hanging drywall first and second floors, north end
  • Started building elevator shaft on stair one walls
  • Continued roofing deficiency repairs, per Gale reports

Posted by Kay Bowman

POSTED: 9:51:00 AM |

Tuesday, February 26, 2013

February 13-February 26, 2013

Henley Construction Company has reported that they have:

  • Started upper level spray fire proofing
  • Continued with air barrier, all areas
  • Installation of fiber cement panel
  • Continued metal roof installation
  • Continued window installation
  • Continued interior stone veneer on exterior cmu
  • Continued pluming rough ins, all areas
  • Continued with electric rough ins, all areas
  • Continued with duct installation, south end
  • Started sprinkler mains and branches, 1st/2nd floors
  • Installed coiling door supports and doors, 1st/2nd floors
  • Installed switchgear
  • Connected storm lines from bldg to flow splitter 1
  • Began fixing roof deficiencies per Gail Reports

Posted by Kay Bowman

POSTED: 1:27:00 PM |

Tuesday, February 19, 2013

January 31, 2013-February 12, 2013

Henley Construction Company has reported that they have:

  • Finished interior spray fire proofing 1st floor SW/SE
  • Continued with air barrier
  • Continued with fiber cement system mock-up
  • Started exterior windows and curtain wall first floor
  • Finished low roof installation at green roof/canopies with exception of deficiency items
  • Continued electric rough-ins all areas
  • Started ductwork mains south west side
  • Continued with plumbing rough-in all areas
  • Started sprinkler rough-in at basement
  • Continued interior wall framing
  • Continued with stone veneer
  • Continued electric rough-ins 2nd and 3rd floors

Posted by Kay Bowman

POSTED: 2:24:00 PM |

Wednesday, January 30, 2013

January 17 to January 30, 2013

Henley Construction Company has reported that they have:

  • Finished low roof fireproofing 1st floor SW/SE;
  • Finished fiber cement panel mock up;
  • Started exterior window installation;
  • Finished low roof installation except some flashings around other trades;
  • Continued elect rough-in all areas;
  • Started duct work, 1st floor SW;
  • started sprinkler rough-in at basement Interior wall framing;
  • Continued interior stone veneer; and 
  • Continued electric rough-ins, 2nd and 3rd floors

Posted by Kay Bowman

 

 

POSTED: 3:33:00 PM |

Wednesday, January 16, 2013

January 3, 2013 to January 16, 2013

Henley Construction Company reports that they have

  • Installed steel framing enclosure, chiller area 
  • Completed interior spray fireproofing 1st Floor SW
  • Started 1st floor SE spray fireproofing
  • Continued installing air barrier;
  • Continued interior wall framing;
  • Started mock up for fiber cement panels
  • Started window flashings
  • Continued with low roof installation
  • Continued with electric panel equipment main electric room
  • Continued testing and installing ducts
  • Continued mechanical and plumbing rough-in all areas
  • Started stone veneer, and 
  • Started  electric rough-ins on second floor.

Posted by K. Bowman

POSTED: 11:35:00 AM |
Entrance of the renovated Gaithersburg Library