Wednesday, August 08, 2012
Henley Construction Company reports that they have
- continued setting steel at the north end;
- finished damp proofing the north end;
- arranged for inspection of the basement waterproofing work;
- started wall rough-ins for the basement;
- began backfill at the north end; and
- started installing mechanical hangers at the north end and in existing areas.
The construction project has been underway for 225 days.
Posted by R.Gale.