Sunday, November 18, 2012
Henley Construction Company reports that they have
- Started interior metal framing;
- Completed exterior metal framing except at book drop;
- Started installation of Stair No. 1;
- Started Installation of high roof;
- Started setting air handling units at the mechanical level and in basement.;
- Poured new electric room slab;
- Poured chiller and generator pads;
- Started setting boilers and pumps in basement;
- Started hangers and duct in basement; and
- Filled existing brick columns with concrete.