Tuesday, January 08, 2013
Henley Construction Company reports that they have
- Delivered and set the chiller;
- Continued with interior light gauge framing;
- Finished stair 1 installation;
- Began fabricating high roof panels;
- Started low roof installation;
- Finished roof blocking;
- Continued electrical and plumbing rough-ins;
- Finished interior CMU walls in basement area;
- Started field measuring for windows; and
- Started light monitor roof.