Tuesday, January 08, 2013
Henley Construction Company reports that they have
- Completed field measurements for exterior fiber cement panels;
- Set emergency generator;
- Continued working on exterior framing and sheathing;
- Started PVC low roof installation;
- Finished roof blocking;
- Finished form rolling sheet metal for high roof installation;
- Hung VAV units at 1st/2nd floor North;
- Worked on duct main/branches at 1st and 2nd floor North;
- Continued interior light gauge framing;
- Continued plumbing and electrical rough-in for all areas;
- Started window fabrication; and
- Finished substrate for light monitor roof.
Posted by R. Gale
CATEGORIES:
POSTED AT: 9:46:00 AM
|