Gaithersburg Library Renovation


Construction updates

Wednesday, January 30, 2013

January 17 to January 30, 2013

Henley Construction Company has reported that they have:

  • Finished low roof fireproofing 1st floor SW/SE;
  • Finished fiber cement panel mock up;
  • Started exterior window installation;
  • Finished low roof installation except some flashings around other trades;
  • Continued elect rough-in all areas;
  • Started duct work, 1st floor SW;
  • started sprinkler rough-in at basement Interior wall framing;
  • Continued interior stone veneer; and 
  • Continued electric rough-ins, 2nd and 3rd floors

Posted by Kay Bowman

 

 

POSTED: 3:33:00 PM |

Wednesday, January 16, 2013

January 3, 2013 to January 16, 2013

Henley Construction Company reports that they have

  • Installed steel framing enclosure, chiller area 
  • Completed interior spray fireproofing 1st Floor SW
  • Started 1st floor SE spray fireproofing
  • Continued installing air barrier;
  • Continued interior wall framing;
  • Started mock up for fiber cement panels
  • Started window flashings
  • Continued with low roof installation
  • Continued with electric panel equipment main electric room
  • Continued testing and installing ducts
  • Continued mechanical and plumbing rough-in all areas
  • Started stone veneer, and 
  • Started  electric rough-ins on second floor.

Posted by K. Bowman

POSTED: 11:35:00 AM |

Tuesday, January 08, 2013

December 22, 2012 to January 2, 2013

Henley Construction Company reports that they have

  • Begun low roof insulation;
  • Started interior spray fireproofing on the first foor;
  • Set the skylight;
  • Continued installing air barrier;
  • Continued interior wall framing;
  • Continued installing ducts in north end on all levels;
  • Scheduled duct testing;
  • Begun sanitary wall rough-ins;
  • Continued electrical rough-ins on north end; and
  • Started temporary heating of the building.

Posted by R. Gale

POSTED: 9:58:00 AM |

Tuesday, January 08, 2013

December 5-December 22, 2012

Henley Construction Company reports that they have

  • Prepared for installation of metal at high roof/monitor roof; 
  • Contiued installing PVC low roof;
  • Begun installation of air barrier;
  • Continued duct work installation at North end of library;
  • Continued interior light gauge framing;
  • Continued plumbing and electrical rough-in for all areas;
  • Completed stone veneer sample panel;
  • Installed steel at chimney infill;
  • Started mechanical, piping in basement and chill water piping;
  • Started installing duct branches on second floor;
  • Continued installing duct branches on first floor north;
  • Started setting door frames on north end; and
  • Tied in storm water lines from roof dreains in all areas.

Posted by R. Gale

POSTED: 9:52:00 AM |

Tuesday, January 08, 2013

November 21-December 5, 2012

Henley Construction Company reports that they have

  • Completed field measurements for exterior fiber cement panels;
  • Set emergency generator;
  • Continued working on exterior framing and sheathing;
  • Started PVC low roof installation;
  • Finished roof blocking;
  • Finished form rolling sheet metal for high roof installation;
  • Hung VAV units at 1st/2nd floor North;
  • Worked on duct main/branches at 1st and 2nd floor North;
  • Continued interior light gauge framing;
  • Continued plumbing and electrical rough-in for all areas;
  • Started window fabrication; and
  • Finished substrate for light monitor roof.

Posted by R. Gale

POSTED: 9:46:00 AM |

Tuesday, January 08, 2013

November 7-November 21, 2012

Henley Construction Company reports that they have

  • Delivered and set the chiller;
  • Continued with interior light gauge framing;
  • Finished stair 1 installation;
  • Began fabricating high roof panels;
  • Started low roof installation;
  • Finished roof blocking;
  • Continued electrical and plumbing rough-ins;
  • Finished interior CMU walls in basement area;
  • Started field measuring for windows; and
  • Started light monitor roof. 

Posted by R. Gale

POSTED: 9:39:00 AM |
Entrance of the renovated Gaithersburg Library
Gaitherburg Library Renovation View of Entrance
 