Wednesday, January 30, 2013
Henley Construction Company has reported that they have:
- Finished low roof fireproofing 1st floor SW/SE;
- Finished fiber cement panel mock up;
- Started exterior window installation;
- Finished low roof installation except some flashings around other trades;
- Continued elect rough-in all areas;
- Started duct work, 1st floor SW;
- started sprinkler rough-in at basement Interior wall framing;
- Continued interior stone veneer; and
- Continued electric rough-ins, 2nd and 3rd floors
Posted by Kay Bowman
POSTED: 3:33:00 PM
|
Wednesday, January 16, 2013
Henley Construction Company reports that they have
- Installed steel framing enclosure, chiller area
- Completed interior spray fireproofing 1st Floor SW
- Started 1st floor SE spray fireproofing
- Continued installing air barrier;
- Continued interior wall framing;
- Started mock up for fiber cement panels
- Started window flashings
- Continued with low roof installation
- Continued with electric panel equipment main electric room
- Continued testing and installing ducts
- Continued mechanical and plumbing rough-in all areas
- Started stone veneer, and
- Started electric rough-ins on second floor.
Posted by K. Bowman
POSTED: 11:35:00 AM
|
Tuesday, January 08, 2013
Henley Construction Company reports that they have
- Begun low roof insulation;
- Started interior spray fireproofing on the first foor;
- Set the skylight;
- Continued installing air barrier;
- Continued interior wall framing;
- Continued installing ducts in north end on all levels;
- Scheduled duct testing;
- Begun sanitary wall rough-ins;
- Continued electrical rough-ins on north end; and
- Started temporary heating of the building.
Posted by R. Gale
POSTED: 9:58:00 AM
|
Tuesday, January 08, 2013
Henley Construction Company reports that they have
- Prepared for installation of metal at high roof/monitor roof;
- Contiued installing PVC low roof;
- Begun installation of air barrier;
- Continued duct work installation at North end of library;
- Continued interior light gauge framing;
- Continued plumbing and electrical rough-in for all areas;
- Completed stone veneer sample panel;
- Installed steel at chimney infill;
- Started mechanical, piping in basement and chill water piping;
- Started installing duct branches on second floor;
- Continued installing duct branches on first floor north;
- Started setting door frames on north end; and
- Tied in storm water lines from roof dreains in all areas.
Posted by R. Gale
POSTED: 9:52:00 AM
|
Tuesday, January 08, 2013
Henley Construction Company reports that they have
- Completed field measurements for exterior fiber cement panels;
- Set emergency generator;
- Continued working on exterior framing and sheathing;
- Started PVC low roof installation;
- Finished roof blocking;
- Finished form rolling sheet metal for high roof installation;
- Hung VAV units at 1st/2nd floor North;
- Worked on duct main/branches at 1st and 2nd floor North;
- Continued interior light gauge framing;
- Continued plumbing and electrical rough-in for all areas;
- Started window fabrication; and
- Finished substrate for light monitor roof.
Posted by R. Gale
POSTED: 9:46:00 AM
|
Tuesday, January 08, 2013
Henley Construction Company reports that they have
- Delivered and set the chiller;
- Continued with interior light gauge framing;
- Finished stair 1 installation;
- Began fabricating high roof panels;
- Started low roof installation;
- Finished roof blocking;
- Continued electrical and plumbing rough-ins;
- Finished interior CMU walls in basement area;
- Started field measuring for windows; and
- Started light monitor roof.
Posted by R. Gale
POSTED: 9:39:00 AM
|
|