Friday, June 29, 2012
During this period, Milestone Construction Company:
- began assembly and installation of shoring braces;
- began selective demolition of exterior masonry walls, roof, and structure;
- began demolishing the existing meeting room wing and removing the debris;
- removed the underground tank;
- began backfill operations; and
- started site utility work.
The construction project has been underway fifty eight days.