Friday, August 10, 2012
During this period, Milestone Construction Company:
- continued saw cutting and removing existing slab on grade;
- continued selective roof demolition;
- installed MH-15, MH-16, and MH-17 and connecting pipes;
- began grading of building pad;
- installed footings along x-gridlines;
- began installation of piers; and
- installed water line stub inside building.
The construction project has been underway 114 days.