Sunday, November 18, 2012
During this period, Milestone Construction Company:
-
Completed Installation of footings and most foundation walls;
-
Began grouting and backfilling of foundation walls;
-
Began digging the trench and other work associated with duct bank installation;
-
Finshed erecting steel framing, required to support the glu-lam beams;
-
Began erection of other steel framing;
-
Began Installation of glu-lam beams;
-
Began installation of wood decking; and
-
Continued with Inspections and testing.