Olney Library Renovation


Construction updates

Thursday, August 23, 2012

August 9 to August 22, 2012

During this period, Milestone Construction Company:

  • continued layout of columns, piers, anchor bolts and footings in all areas;
  • removed beam from shoring under one of the roof sections;
  • held a steel pre-con meeting;
  • began erecting steel; and
  • completed approximately 50% of the beams in the center high roof area.

The construction project has been underway 142 days.  A construction crane is now on site for erecting the steel.

Posted by R. Gale

POSTED: 3:46:00 PM |

Friday, August 10, 2012

July 26 to August 8, 2012

During this period, Milestone Construction Company:

  • completed concrete slab removal;
  • continued layout of peers and footings at the addition area;
  • completed approximately 60% of water line installation;
  • completed selective masonry demolition; and
  • held an electrical pre-con meeting.

The construction project has been underway 128 days.  98% of demolition work is complete and Milestone expects to begin erecting steel in the next two weeks.

Posted by R. Gale

POSTED: 7:46:00 PM |

Friday, August 10, 2012

July 12 to July 25, 2012

During this period, Milestone Construction Company:

  • continued saw cutting and removing existing slab on grade;
  • continued selective roof demolition;
  • installed MH-15, MH-16, and MH-17 and connecting pipes;
  • began grading of building pad;
  • installed footings along x-gridlines;
  • began installation of piers; and
  • installed water line stub inside building.

The construction project has been underway 114 days.

Posted by R. Gale

POSTED: 7:34:00 PM |

Friday, August 10, 2012

June 28 to July 11, 2012

During this period, Milestone Construction Company:

  • continued cleaning salvaged bricks (removal of loose mortar particles); 
  • continued concrete slab removal;
  • continued miscellaneous selective demolition;
  • continued debris removal
  • started layout of footings at the addition area; and
  • began tying rebar mats.

The construction project has been underway 100 days.

Posted by R. Gale

 

POSTED: 7:28:00 PM |
Entrance of the renovated Olney Library
Olney Library Renovation View of Entrance
Categories
 

Library Policies | Friends of the Library | Library Board | Library Jobs | Contact Us

Last edited: 11/6/2007