PRIMARY / ARTERIAL RESURFACING PROGRAMS 


The Primary/Arterial Roads Resurfacing Programs are instituted to protect and maintain the County’s primary roadway transportation infrastructure. The County has approximately 957 lane miles of Primary/Arterial roads. The scope of work includes milling, repair, bituminous concrete resurfacing, patching and revitalization. Roadway resurfacing is the process of applying a new wearing surface on County-maintained roadways throughout the County. This Program provides for systematic, full-service and coordinated revitalization to enhance access and safety for all users.

 

2013 CONSTRUCTION SEASON: Update: 4/8/2013

Click on the road name (if underlined) to read or download a Project Newsletter describing the scope of the project.

Check back periodically as projects get added or scheduled. This schedule may be changed and substitutions may be made at any time due to weather or operational reasons.

Road Name From: To:

Project Scope

Start Date 

 Status

Colesville Road MD 97 MD 410

HMA

5/6/2013

 
Contour Road Lost Knife Rd. Odendhal Ave.

HMA

4/8/2013

 
Fenton Street Wayne Ave. Cameron St.

HMA

TBD

 
Middlebrook Road MD 355 Great Seneca Hwy.

2x Micro

Postponed

Postponed/WSSC

Mink Hollow Road MD 108 End of Maintenance

HMA

4/9/2013

 
Odendhal Avenue Lost Knife Rd. Goshen Rd.

HMA

4/8/2013

 
Old Stage Road Tilden La. Hitching Post La.

Patching

TBD

 
Omega Drive Key West Ave. I-270 Ramp

2x Micro

TBD

 

Piney Meetinghouse Rd. Cavanaugh Dr. Boswell La.

HMA

4/8/2013

 
Randolph Road Veirs Mill Rd. Connecticut Ave.

HMA

TBD

 
Ridge Drive Glen Mill Rd. Watts Branch Dr.

Patching

Spring 2013

 
Seven Locks Road Montrose Rd. Tuckerman La.

HMA

Summer 2013

 
Stoney Creek Road Travilah Rd. River Rd.

HMA

4/22/2013

 
Tildenwood Drive Montrose Rd. Old Stage Rd.

Patching

TBD

 
Westlake Drive Democracy Blvd. Tuckerman La.

HMA

5/13/2013

 

Click on the underlined link(s) provided below to view respective project schedules:

ARRA Federally Funded Paving Program
Patching Full-Depth Permanent Patching
2x Micro Double-Shot Micro Resurfacing
HMA Hot Mix Asphalt Paving

TBD = Schedule for this project To Be Determined at a later date. 

 

 

 

 

Last edited: 4/9/2013