The Primary/Arterial Roads Resurfacing Programs are instituted to protect and maintain the County’s primary roadway transportation infrastructure. The County has approximately 957 lane miles of Primary/Arterial roads. The scope of work includes milling, repair, bituminous concrete resurfacing, patching and revitalization. Roadway resurfacing is the process of applying a new wearing surface on County-maintained roadways throughout the County. This Program provides for systematic, full-service and coordinated revitalization to enhance access and safety for all users.

 

2013 CONSTRUCTION SEASON: Update: 6/14/2013

Click on the road name (if underlined) to read or download a Project Newsletter describing the scope of the project.

Check back periodically as projects get added or scheduled. This schedule may be changed and substitutions may be made at any time due to weather or operational reasons.

Road Name From: To:

Project Scope

Start Date 

 Status

Ambleside Drive Betteker La. Glen Rd.

Patching

TBD

 
Arliss Street Piney Branch Rd. Flower Ave.

HMA

Fall 2013

 
Club House Road Watkins Mill Rd. Centerway Rd.

HMA

6/6/2013

10%

Colesville Road MD 97 MD 410

HMA

5/6/2013

100%

Contour Road Lost Knife Rd. Odendhal Ave.

HMA

4/8/2013

100%

Diamondback Drive Key West Ave. End

Patching

TBD

 
Diamondback Drive Sam Eig Hwy. Muddy Branch Rd.

HMA

Summer 2013

 
Dufief Mill Road Darnestown Rd. Tavilah Rd.

HMA

Fall 2013

 
Fenton Street Wayne Ave. Cameron St.

HMA

Summer 2013

 
Fernwood Road Rockledge Dr. Democracy Blvd.

HMA

Fall 2013

 
Flower Hill Way Woodfield Rd. Snouffer School Rd.

Patching

TBD

 
Lloyd Road Glen Mill Rd. End

Patching

TBD

 
Marinelli Road Executive Blvd. MD 355

2x Micro

4/15/2013

50%

Mateny Road Great Seneca Hwy. Creamery Hill Dr.

2x Micro

5/13/2013

50%

Middlebrook Road MD 355 Great Seneca Hwy.

2x Micro

On Hold

Postponed

Mink Hollow Road MD 108 End of Maintenance

HMA

4/9/2013

100%

Montgomery Village Ave. Wightman Rd. Lost Knife Rd.

Patching

Spring 2013

100%

Newbridge Drive River Rd. Democracy Blvd.

2x Micro

4/29/2013

50%

Newport Mill Road Veirs Mill Rd. University Blvd.

2x Micro

5/8/2013

5%

Notley Road MD 650 Bonifant Rd.

HMA

Fall 2013

 
Odendhal Avenue Lost Knife Rd. Goshen Rd.

HMA

4/8/2013

100%

Old Stage Road Tilden La. Hitching Post La.

Patching

Spring 2013

50%

Omega Drive Key West Ave. I-270 Ramp

2x Micro

TBD

 

Parkland Drive Veirs Mill Rd. Aspen Hill Rd.

HMA

Fall 2013

 
Piney Meetinghouse Rd. Cavanaugh Dr. Boswell La.

HMA

4/8/2013

100%

Randolph Road Veirs Mill Rd. Connecticut Ave.

HMA

Summer 2013

 
Ridge Drive Glen Mill Rd. Watts Branch Dr.

Patching

Summer 2013

 
Security Lane Woodglen Dr. MD 355

2x Micro

4/7/2013

50%

Seven Locks Road Montrose Rd. Tuckerman La.

HMA

Summer 2013

 
Silo Way Windmill La. Twig Rd.

2x Micro

4/1/2013

50%

Snoeshoe Lane Sugarbush La. Edson La.

2x Micro

4/25/2013

50%

Stedwick Road Mont. Village Ave. Watkins Mill Rd.

HMA

Spring 2013

60%

Stewartown Road Mont. Village Ave. Goshen Rd.

Patching

TBD

 
Stoney Creek Road Travilah Rd. River Rd.

HMA

4/22/2013

100%

Sugarbush Lane Tuckerman La. Snoeshoe La.

2x Micro

4/22/2013

50%

Tilden Lane Old Stage Rd. Cul de sac

Patching

Summer 2013

 
Tildenwood Drive Montrose Rd. Old Stage Rd.

Patching

Summer 2013

 
Tucker Lane MD 108 MD 650

2x Micro

5/3/2013

5%

Tuckerman Lane MD 355 MD 355

Patching

TBD

 
Twig Road Good Hope Rd. Windmill La.

2x Micro

4/17/2013

50%

Wayne Avenue Colesville Rd. Georgia Ave.

HMA

Fall 2013

 
Weller Road Georgia Ave. Connecticut Ave.

2x Micro

5/6/2013

5%

Westlake Drive Democracy Blvd. Tuckerman La.

HMA

5/13/2013

100%

Windmill Lane Good Hope Rd. Twig Rd.

2x Micro

4/20/2013

50%

Woodfield School Road Woodfield Rd. Hawkins Creamery Rd.

Patching

TBD

 
Woodglen Drive Nicholson La. Edson La.

2x Micro

4/9/2013

50%

Click on the underlined link(s) provided below to view respective project schedules:

ARRA Federally Funded Paving Program
Patching Full-Depth Permanent Patching
2x Micro Double-Shot Micro Resurfacing
HMA Hot Mix Asphalt Paving

TBD = Schedule for this project To Be Determined at a later date. 

 

 

Last edited: 6/14/2013