Location or Subdivision

Project Scope

Start Date 

Status 

Countryside Subdivision

Residential Roadway Resurfacing

   
Ednor Acres/Cliftonbrook Subdivision

Residential Asphalt Paving

TBD

 
Foxhall

Residential Concrete Repair/Replacement

June 2013

0%

Franklin Knolls Subdivision

Residential Rehabilitation

7/2/2012

50%

Mink Hollow Road

Primary/Arterial Asphalt Paving

4/9/2013

100%

Oakview

Residential Concrete Repair/Replacement

June 2013

0%

Oakwood/Perrywood Subdivision

Residential Roadway Resurfacing

4/22/2013

25%

Peachwood Subdivision

Residential Asphalt Paving

4/1/2013

70%

Spring Oak Estates

Residential Roadway Resurfacing

4/22/2013

50%

Tamarack

Residential Concrete Repair/Replacement

June 2013

0%

Tucker Lane

Primary Double Micro Surfacing

5/3/2013

5%

TBD = Schedule for this project To Be Determined at a later date.
 

 

 