| Return to: Up County Projects | |||||
|
Clarksburg
Fire Station To
be located on Frederick Road
north of Clarksburg Road Clarksburg, MD 20871 Project
Team
Architect Hughes Group Architects 22630 Davis Drive Suite Sterling VA 20164 (703) 437-6600 Montgomery County
Government
Department of General Services Project Manager Rouben Ghazarian, P.E. (240) 777-6056 Team Leader Suresh Patel (240) 777-6179 |
![]() |
||||
| Project Description: This project provides for a
new Fire/Rescue Station in the Clarksburg area and the purchase of
associated fire apparatus. The new facility will be located on an
acquired site located on MD 355 (Frederick Road) just north of
Clarksburg Road. The new station will be constructed in
accordance with the requirements for a Class I Fire Station. A
Class I Fire Station is 19,550 to 20,135 square feet in size and
includes apparatus bays, dormitory and support space, personnel living
quarters, administrative offices and meeting/training room.
Additionally, this station will include offices for a Battalion Chief,
a Police satellite facility, space for the Up County Regional Services
Center and personal protective equipment storage totaling 2,600 square
feet. The total square footage of this station will be 22,600 square
feet. On-site parking will be provided. Fire/Rescue apparatus to
be purchased for this station includes an aerial truck, a tanker and a
brush truck.
A
new station is necessary
in this area due to the present and projected population density for
the Clarksburg area. Clarksburg is expected to increase from
a
few thousand residents to more than 25,000. The Clarksburg
Town
Center is envisioned to include a mix of housing, commercial, retail,
recreation and civic uses with the Clarksburg Historic District as the
focal point.
This
project is recommended
in the Fire, Rescue, Emergency Medical Services and Community Risk
Reduction Master Plan approved by the County Council in October 2005
and the MCFRS Station Location and Resource Allocation Work Group,
Phase I Report, “Need for Upcounty Fire-Rescue Resource
Enhancements, October 14, 1999. Development of this facility
will
help Montgomery County meet the NFPA 1710 Guidelines.
Funding: Important Documents Natural Resources Inventory (NRI)/
Forest Stand Deliniation (FSD) Plan
Natural Resources Inventory (NRI)/ Forest Stand Deliniation (FSD) Approval Letter MNCPPC Mandatory Referral for Site Selection (April 29, 2010) Project Status: On May 13, 2010, the Planning Board approved Mandatory Referral for site selection. The approved site is located on Frederick Road just north of the Clarksburg Road intersection (adjacent to the Damascus Community Bank). The site consist of two parcels each two acres in size. The total project site is 4.04 acres. The County settled both properties on August 4, 2010 and started the design phase at that time. The Architect/Engineer for the project is Hughes Group Architects of Sterling, Virginia. The entire design phase is expected to take eighteen months. The project team provided a public presentation of the project on February 28, 2011 at the "cottage" at the intersection of Route 355 and Stringtown Road in the shopping center.” The Design Development Phase was submitted on July 12, 2011 and documents are presently under quality control review.
Clarksburg Fire Station Community Presentation (February 28, 2011) |
|||||
Project
Images
|
|||||
|
Links of
Interest |
|||||
Division of Building Design and Construction - Department of General Services
11th floor, 101 Monroe Street Rockville MD 20850