|
|
Judicial
Center
Annex
50
Maryland Ave
Rockville, Maryland 20850
Project
Team:
Architect
AECOM
Design
3101 Wilson, BLVD, Suite 900
Arlington, VA 22201
Montgomery
County Government
Department of General Services
Office of Special Projects
Hamid
Omidvar, AIA, Chief
240-777-6126
Project
Manager
Randall Hawkins
240-777-6099
|

|
| |
Important
Notices
NOISY WORK
Between the dates from September 10, 2012 through November 1, 2013, a small portion of the overall construction work will take place in the evenings to early mornings between the hours of 8:00 pm through 7:00 am. This work must be completed during these times to avoid disrupting the Circuit Court. Regrettably, vibrations from the construction activity reverberate through the entire Judicial Center interfering with our electronic, digital court recording system which can make the recording of the court process unintelligible. Consequently, a transcript of the legal proceedings cannot be provided to the litigants or appellate courts which could cause devastating, unintended consequences for litigants. Additionally, the Circuit Court handles court and jury trials which can include criminal cases with sentences involving of life or death, family matters involving divorce, custody and termination of parental rights, which are highly emotional and can be catastrophic to the family element, and civil cases where judges and juries will determine the fate of businesses, medical malpractice suits, foreclosures, etc. All of these matters mentioned and many others not referenced are determined daily in the Judicial Center.
Every effort will be made to minimize noise. The work will include the following:
- Demolition and Reconstruction of New Maryland Avenue Entrance (Noise generating activities include saws, chop saw, concrete cutting saws, screw guns, plaster mixers, man lifts-backup alarms, debris placed in dumpsters, hammer drills, power-actuated fasteners, and Bobcat motors.) This activity will approximately start on September 10, 2012 and conclude June 1, 2013. The typical work shift is from 8:00 PM to 4:00 AM. All major noise generating work will occur before 11:00 PM or during the day on Saturdays.
-
Demolition and Installation of New Roof at Maryland and Monroe Entrances (Noise generating activities will include grinding and possible chipping of concrete, quick saws, scrapers, saws, crane, compressors, back-up alarms, delivery trucks, screw guns, hammer drills, and placement of debris in dumpsters.) The typical work shift is from 8:00 PM to 4:00 AM. All major noise generating work will occur before 11:00 PM or during the day on Saturdays.
- Demolition and Reconstruction of New Monroe Street Entrance (Noise generating activities include saws, chop saw, concrete cutting saws, screw guns, plaster mixers, man lifts-backup alarms, debris placed in dumpsters, hammer drills, power-actuated fasteners, and Bobcat motors.) This activity will approximately start on June 1, 2013 and conclude on November 1, 2013. The typical work shift is from 8:00 PM to 4:00 AM. All major noise generating work will occur before 11:00 PM or during the day on Saturdays.
We apologize for any inconvenience this may cause.
If you have questions or concerns during the evening operations, please contact Samuel Gillespie, Superintendent for Tompkins Builders, Inc., at (202) 438-0801 or Ray Steinmetz, Montgomery County Construction Representative, at (240) 672-5389. For questions or concerns during the day please contact Randall Hawkins, Montgomery County Representative at (240) 777-6099 or Bill Bishop, Tompkins representative at (202) 369-9721. For information regarding the Montgomery County Noise Ordinance program, please visit the following
http://www.montgomerycountymd.gov/dectmpl.asp?url=/Content/dep/community/ordinance.asp.
|
Project Status: Construction Phase
Construction Progress Bulletin
- The Maryland Avenue entrance completion date has been pushed back to June.
- The Pilkington glass system on the east façade is almost completely installed except for areas that still require coordination with other trades at the perimeters. The construction of the stair structure at the south end has been finished and the stairwell has begun to be enclosed with glass.
- Gyp board room partitions are almost completely installed on Terrace, 1st, and 2nd levels
- A mock up of a Courtroom with furniture should be complete by May for the judges to tour and approve.
Construction Progress Images
 |
|
April 2013:
Pictured is the south-east façade. The stair on the south end of the south send of the building is in the process of being enclosed. The yellow material is a spray applied air barrier membrane applied for insulation purposes. The blue material is a membrane that prevents water penetration.
|
 |
|
April 2013:
Pictured is west façade of the building. All the glass and fins are installed. The blue membrane covered fins will eventually receive a copper colored aluminum panel sheathing.
|
Project Description
This
project involves an addition to
and renovation of the existing Judicial Center. The Judicial Center
Annex is a six story building with one level underground parking and
one level mechanical penthouse. The Annex provides ten additional
courtrooms and administrative spaces. The renovation of the existing
judicial center includes upgrading interior spaces, mechanical,
electrical and plumbing upgrades. The project will be designed to
comply with Leadership in Energy and Environmental Design (LEED)
guidelines for LEED Silver (potentially Gold certification) which
includes a green roof and roof mounted photovoltaic panels. The
existing plaza and green spaces will be redesigned to invite public use
of the space. The green space will include a water fountain, new trees,
benches and a Memorial Walkway to receive the memorial plaques that
will be relocated to allow for the construction of the Annex. Refer to
the site plan image for the location of the Memorial Walkway.
The
project consists of three
phases. Phase one includes the existing Judicial Center HVAC renovation
for floor 6-9 and the penthouse roof . Phase two includes the
construction of the Annex and the phase three encompasses the interior
renovation and upgrades of the remaining area of the existing Judicial
Center.
Project
Animation
Funding
Memorial Walkway
|

(click
to view
image in full
size) |

(click
to view
image in full
size) |
|
Links
of Interest
Montgomery
County
Circuit Court
Government Center Complex, Rockville
|